Spring Center, the 440-acre planned development project in Spring Hill will undergo rezoning to accommodate the town center, with surrounding multi-family and single-family homes. In a 5-0 vote, the Board of County Commissioners voted on September 11, 2018 to approve the rezoning petition with modified conditions and clarifications of language in some portions of the development’s plan.
The modifications recommended by the Planning and Zoning Commission (P&Z) require that the final design be coordinated with the county engineer, and that alternative routes be sought, rather than employing Chalmer street and Stephanie Drive.
The condition states, “… for Stephanie Drive and Chalmer street to be used as alternative access points, the developer must demonstrate to the county that reasonable efforts have been made to obtain access to the Spring Center through the undeveloped properties.”